Contractors who want their mechanic’s liens to take priority over a mortgage under the relation-back doctrine and Minn. Stat. Sec. 514.05 must prove that their contribution of material or labor relates directly to one continuous project of improvement to the property — not merely to the overall project of improvement.

Priority requires continuous improvements

Contractors who want their mechanic’s liens to take priority over a mortgage under the relation-back doctrine and Minn. Stat. Sec. 514.05 must prove that their contribution of material or labor relates directly to one continuous project of improvement to the property — not merely to the overall project of improvement.